April Construction Update

Blog

Apr 25, 2024

Construction at the Woodfibre LNG site continues, focused on work to prepare the site for facility construction later this year, as well as preparatory work to welcome the floatel, which will house 652 non-local workers outside of the community of Squamish. In accordance with existing permits from the District of Squamish, clearing and grubbing the side slope continues in preparation for blasting later this spring – which will make it possible for the construction of the marine terminals to begin during the next marine window of least risk (August 2024-January 2025).

To support the arrival of the floatel, installation of gangways onto the site have occurred, as well as construction of a water distribution line to support the floatel.

Blasting is anticipated within normal business hours.