Hi Dan,
Thanks for your questions. BC Hydro has developed three interconnection options (alternatives) for the Woodfibre LNG Project. Each option involves a temporary solution to provide power to Woodfibre LNG by March 2017, and a permanent solution to provide a full, redundant power supply at an undetermined date. For information on the three interconnection options, please visit the specific Woodfibre LNG and Fortis BC webpage on the BC Hydro website.