Hi Martin,

Thank you for the questions.

Our power requirements for the Woodfibre LNG Project will be approximately 140 MW under normal conditions and 185 MW under peak loading.  Air cooling is expected to result in approximately a 2% production decrease. Those numbers will be further refined as part of the parallel FEED currently underway.  That being said – if we assume that the Woodfibre LNG plant uses 140 MW continuously (365 days per year; 24 hours per day), it would use 1,226 GWh annually.